Appearance
IEEE 9-bus system
The Western System Coordinating Council (WSCC) three-machine, nine-bus system is a standard benchmark for power-flow and transient studies. This chapter develops a three-phase electromagnetic-transient (EMT) representation of the benchmark and verifies its 60 Hz steady state against the conventional phasor solution.
1. Study objective
The reference case is normally specified as a positive-sequence phasor dataset containing bus, branch, transformer, generator, and load data. An EMT implementation requires an explicit time-domain model for each entry. The principal objective is to determine whether those element models reproduce the published operating point when observed at the fundamental frequency.
Three result sets are compared:
- the published load-flow solution;
- a Newton–Raphson power-flow solution evaluated from the circuit file;
- the settled RMS values obtained from a 200 ms EMT simulation.
This comparison tests the consistency of the network representation without introducing synchronous-machine dynamics.
2. EMT representation
2.1 Generator equivalents
Each generator is represented by an ideal balanced three-phase voltage source behind a 1 mΩ series resistance. Source magnitude and phase are set equal to the solved terminal-bus values. The three generator buses therefore act as prescribed electrical boundary conditions; deviations at the remaining buses can be attributed to the network and load models rather than to machine initialization or controller dynamics.
2.2 Loads
The three loads are represented by constant impedances selected to absorb their specified MW and MVAr at the corresponding solved bus voltage. For a balanced three-phase load expressed in terms of total complex power and line-to-line voltage, the equivalent per-phase impedance is
The constant-impedance formulation introduces no additional control dynamics and matches the specified power at the reference operating point.
2.3 Transformers
The three step-up transformers retain the benchmark leakage reactances on the 100 MVA base. Their winding resistances are zero, consistent with the source dataset. The EMT models also include 1% magnetizing-current branches; this distinction is relevant when transformer terminal currents are compared with the load-flow result.
2.4 Transmission lines
Each 230 kV branch is represented by a distributed-parameter Bergeron travelling-wave model rather than a lumped π section. The positive-sequence
The resulting line parameters are:
| Line | |||||
|---|---|---|---|---|---|
| 4–5 | 0.0100 | 0.0680 | 0.176 | 329 | 290 |
| 4–6 | 0.0170 | 0.0920 | 0.158 | 404 | 320 |
| 5–7 | 0.0320 | 0.1610 | 0.306 | 384 | 589 |
| 6–9 | 0.0390 | 0.1738 | 0.358 | 369 | 662 |
| 7–8 | 0.0085 | 0.0576 | 0.149 | 329 | 246 |
| 8–9 | 0.0119 | 0.1008 | 0.209 | 367 | 385 |
3. Time-step selection
A Bergeron line stores the incident wave from each terminal and returns it after one propagation delay. The integration step must therefore be shorter than the smallest line delay. Line 7–8 is the limiting branch, with
4. Steady-state validation
4.1 Measurement procedure
One RMS meter is connected to each bus. Every meter evaluates line-to-line voltage over a sliding one-cycle window. Once the window is full and the network has settled, its output can be compared directly with a 60 Hz phasor magnitude.
The following table reports the published solution, the Newton–Raphson result obtained with Power Flow, and the settled meter value from the 200 ms EMT simulation.
| Bus | Published | Newton-Raphson | EMT meters | EMT − published |
|---|---|---|---|---|
| 1 | 1.04000 | 1.0400 | 1.040001 | |
| 2 | 1.02500 | 1.0250 | 1.025000 | |
| 3 | 1.02500 | 1.0250 | 1.024999 | |
| 4 | 1.02531 | 1.0253 | 1.025170 | |
| 5 | 0.99972 | 0.9997 | 0.999584 | |
| 6 | 1.01225 | 1.0123 | 1.012299 | |
| 7 | 1.02683 | 1.0268 | 1.026689 | |
| 8 | 1.01727 | 1.0173 | 1.017191 | |
| 9 | 1.03269 | 1.0327 | 1.032657 |
4.2 Voltage error
The maximum bus-voltage difference between the EMT result and the published solution is
4.3 Relation between the phasor and EMT line models
The two calculations use different mathematical formulations. The load-flow calculation solves a set of complex algebraic equations at 60 Hz using lumped π branches. The EMT calculation advances a differential-algebraic system through 4,000 time steps and represents each transmission line by delayed travelling waves.
For a lossless distributed line, the equivalent π parameters at angular frequency
For this network,
4.4 Current cross-checks
The phase-
At the slack source, the EMT current is 2,601 A, compared with 2,586 A from the load flow. The approximately 0.6% difference is primarily due to the transformer magnetizing branches, which are present in the EMT model but absent from the reference load-flow model. Reducing the magnetizing-current settings on all three transformers from 1% to 0.001% lowers the EMT current to 2,589 A.
5. Exercises
Transformer winding resistance. Set
r_hv_lv_pu = 0.005on each transformer. Compare the bus-voltage magnitudes and the decay of the source-current DC offsets with the original case. Explain why winding resistance has little effect on the load-flow operating point but a substantial effect on the EMT startup transient.Time-step sensitivity. Repeat the simulation with
and compare the settled voltages with the 50 µs results. Then investigate what occurs when the time step exceeds the 246 µs propagation delay of line 7–8. Relate the observed behavior to the delay-line storage requirement. Single-contingency study. Open either line 4–5 or line 4–6 and calculate the resulting redistribution of line power. The line open/short sample provides an example of the required switching arrangement.
Dynamic source substitution. Replace one ideal source with a synchronous machine and excitation system, following the generator controls sample. Use the load-flow solution as the dynamic model's initial condition, and distinguish network-model errors from electromechanical rotor response.